Mission Critical
T5 engaged Frontier to support the transformation of a former manufacturing facility into a high-density data center designed to support the rapid growth of AI infrastructure.

Frontier retrofitted a 250,000-square-foot brownfield facility, delivering administrative spaces, security infrastructure, and operational improvements that enabled its conversion into a high-density data center campus designed for next-generation computing workloads.
Services: Data Center Retrofit
Square Feet: 250,000 square feet
Completed: 2026
- 70-acre campus
- Brownfield facility retrofit
- 117 MW power capacity
- AI-ready infrastructure
- Low-voltage security infrastructure
- Interior reconstruction
- Exterior improvements
- Accelerated 24-hour construction
Project Overview
Originally developed as a manufacturing facility, the 70-acre campus was transformed into a high-density data center designed to deliver reliable power, scalable infrastructure, and high-speed connectivity for next-generation computing workloads. Frontier completed the retrofit of the 250,000-square-foot facility, delivering office and administrative areas, conference rooms, security infrastructure, operational spaces, and exterior improvements required to support the site’s next phase of operation.
The project demanded an accelerated delivery schedule, with hundreds of workers deployed and 24-hour construction operations implemented at key phases to support speed-to-market objectives. The completed campus now provides 117 MW of capacity across a 70-acre site, supporting a scalable computing environment with the infrastructure required for AI and other high-performance workloads.